Installation Guide • 5 min read

How Long Does Flooring Installation Take?

Learn what factors can influence the timeline of a flooring installation project.

Back to All Articles
Published July 20265 min read
Key Article Takeaways
Standard 1,000 sq ft residential LVP installation takes 2 to 3 full working days.
Wood material acclimation requires 48-72 hours inside the home before installation.
Subfloor leveling compound requires 12 to 24 hours of drying cure time.
Baseboard replacement, stair scribing, and nosing transitions add detail installation time.
01

Phase 1: Material Acclimation & Site Preparation (Day 1)

Before installation begins, hardwood and wood-composite materials must acclimate inside the climate-controlled job site for 48 to 72 hours. This step equalizes moisture content between the flooring and the room air. On Day 1 of active installation, technicians clear existing carpet/tack strips, perform subfloor moisture tests, and inspect subfloor flatnesses.

02

Phase 2: Subfloor Leveling & Underlayment Setup (Day 1-2)

If subfloor dips exceed 3/16" over a 10-foot radius, self-leveling cement compound is mixed and poured. This layer requires 12 to 24 hours to cure fully before plank laying can commence. Installing high-density acoustic underlayment or vapor barriers follows immediately after compound curing.

"Skipping subfloor leveling creates hollow footstep sounds and eventually breaks plank click-lock joints."

2. Phase 2: Subfloor Leveling & Underlayment Setup (Day 1-2)
HD Flooring On-Site Craftsmanship
03

Phase 3: Plank Laying & Precision Custom Scribing (Day 2-3)

Plank installation proceeds rapidly — professional crews lay between 400 to 800 sq ft of click-lock LVP or laminate per day. Complex room layouts, door casing undercuts, hearth scribing, and stair nosing coving require careful hand-crafting, adding specialized time.

04

Phase 4: Baseboard Trimming, Transitions & Final Site Cleanup (Day 3-4)

The final phase involves re-installing baseboards or installing quarter-round shoe moldings, T-molding transition strips between doorways, vacuuming all installation dust, and conducting a final quality inspection with the homeowner.

Got Questions?

Frequently Asked Questions

Yes, rooms must be cleared of furniture and personal items before crew arrival. Most installation teams offer furniture moving services upon request.